Imported Material Resources Budget Units & Duration set to zero

Hi Everyone, 

i just imported a programme, i discovered that durations & budget units of material resources are set to zero, any advice ?

Best regards,

A
Alain De leon 👤 Member for 13 years 11 months

check your resources if there is price / unit and quantity on the budgeted units