Duration error - I entered days & it took it as hours.

I am new to P6 using P6v7.

I entered activities & their durations the normal way & added resources to the activities. It is showing like this: -

Original Duration Column as 20d [ fine as I entered 20 ]

Budgeted Units as 20h in Bottom Layout - Resources TAB. [ when i entered 20 as days, it took as hours]

This affected my Budgeted Total Cost Column, as my cost is taking the durations from the resources (in hrs.)

 

can anybody help, i guess some adjustment required in Preferences but i don t know where.

 

 

H
Håkon Haukebøe 👤 Member for 13 years 8 months

Try:

Edit - > user preferences - > Time units. There you can choose Units and Durations to Day.

 

Haakon

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts