How to install P6 version 8.3 stand alone?

I'm trying to install Primavera P6 V8.3 standalone on a notebook with windows 8 but I can't make it work. I would like to install it with SQL, if possible. Does anyone have some tutorial or some tips? Thanks!

R
Ronald Winter 👤 Member for 23 years 5 months

You cannot use the Standalone option to install anything other than the Oracle Express database.  If you want SQL Express, you will first need to download it from the Microsoft website and then install it before installing P6.  Instead of using the Standalone option, use the Configuration option.  This is not a simple and painless process.   I recommend that you ask a Certified Primavera Provider to do this for you.  Good luck!