Hi Everyone,
i just imported a programme, i discovered that duration of material resources are set to zero unlike the activities durations, any advice ?
Best regards,
Hi Everyone,
i just imported a programme, i discovered that duration of material resources are set to zero unlike the activities durations, any advice ?
Best regards,
check the activity type on the activity details -select task dependent