How to show Primavera P6 dates in month-year (mmm-yy) format

The date formats available in Primavera P6 are very limited and to best of my knowledge, you cannot get the mmm-yy (month-year) format straight out of the box. You might want to display dates in mmm-yy if you don't want to show exact dates in issued schedules.

This P6 video outlines a workaround using UDF that can be used to achieve mmm-yy date format.

Microsoft Project Quick Tip: Assign Actual Start & Finish Dates to Tasks

While one can update Actual Start and/or Actual Finish dates in Microsoft Project by displaying these columns, my preferred method is using the Task Details Form which is very similar to the Activity Details Form in Primavera P6.

In this short video, I show how to enable and use the Task Details Form to update actual dates for project tasks.