How to create Cumulative Late Curve in P6
Forum Sponsor
Top Posters
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
there is no link just go to view show on bottom resource usage profile and select either the early or late dates
view show on bottom resource usage profile then select
remaining early and or remaining late
Hi , Please send me the steps for creating late curve and early curve. Thanks, Rajeev
Hi Arnold
Please send this document in my mail : [email protected]
Thank you very much
Hi Arnold,
Please share with me the steps.
My email is [email protected]
Regards,
Siraj
Hi Arnold,
Please, also send me the steps on how to create the comulative late curve in P6.
This is my email : [email protected]
Thanks & Regards
karim
Early & late curves can be generated straight away once you have resources loaded schedule in P6.
You can find these curves ready made for you in activity usage profile window. Right click on the graph and select At activity usage profile options. Under Bar/curves, select Remaining Early or Remaining late curve.
Cheers...
Hi Arnold,
Please, also send me the steps on how to create the comulative late curve in P6.
This is my email : [email protected]
Thanks & Regards
jamil
Hi Arnold,
pls send me also..(s -curve late and early)
mail: [email protected]
Thanks in advance
Sunil.
hi, I'm new in this forum & I ask you to teach me how to create a s-urve conjugated with global change ??? thank you.
Hi Mr Arnold
can you send me also
[email protected]
Thanks
Arnold, send to me too..
[email protected]
tqvm
I do not use P6 but using Google found the following link that shows a way to generate the data for Excel, then with a knowledge of Excel or using an Excel template you can generate the combined curves.
http://primaverarena.com/wp-content/uploads/2010/05/S-curve-creation-for-P6.pdf
The following links provides some tutorials that might be of interest and perhaps showing a different approach.
http://www.toolboxforplanning.com/p/tutorials.html
http://www.toolboxforplanning.com/2010/10/excel-2003-tutorial-creating-progress-s_16.html
You can download their template or a modified version I just created to include early and late banana curves from the following link.
http://www.mediafire.com/download.php?ekc33bya2nd44e4
I prefer to display on the vertical axis the absolute values instead of percentages as it can create confusion when contract value changes.
Because of the way P6 stores period performance on uncompleted activities there can be discrepancies on displayed period performance if you do not make use of financial periods. The following link can provide you with an introduction on this issue.
http://primaverablog.in/2011/03/financial-periods-2/
Hope this help.
Regards,
Rafael
can you please send me the steps and the required software( or plugin) to be able to generate these curves?
[email protected]
can you please send me the steps and the required software( or plugin) to be able to generate these curves?
[email protected]
can u send me to [email protected]
Hey Guys,
Could please send me the procedure?Thanks!email: [email protected]
Arnold will you please send me the steps? [email protected]
Thank you
Hi Arnold,
Would you please send me the details also; [email protected].
Cheers
Christian
Hi Arnold,
Would you please send me the details also; [email protected].
Cheers
Hi Arnold, may I request you a copy of the instructions about how to create the cumulative curve?
I will be thankful.
My email address is: [email protected]
Thanks,
German.
good day arnold,
this may a bit late
still, please could you send me the steps
iam new in p6
appreciate your help
my eadd; [email protected]
me too, really need it [email protected]
Dear All,
That can be done from the Assignment screen to copy the resorces usage and to paste in excel sheet.
Regards,
hi
can u send me also
[email protected]
best regards.
Hi Arnold,
Can you kindly send it to me as well. please. [email protected]
Thank you.
JRF
Just remember you will need two sets of early and late S curves (two banana curves). One for the baseline schedule and another for the current schedule that shall not only display actual performance up to data date but also shall display projected early and late S curves after data date.
Also remember to apply postings to financial periods if your software is not capable of display correct values without using periods, an unneeded patch in more capable software. At least P6 is better than SureTrak that was not able to display correct values and did not provided such patch. P6 requires such patch same as P3 but at least P6 allows you to edit closed periods while P3 does not. The BUG has to do with the design of the mathematical distribution of activities that span performance over two updating periods, for most people the way around using financial periods is ok.
pls send me here [email protected]
i will be thankful ..........
Hi Arnold,
Admit I am very late in tihis forum. But much appreciate if you could send me the late and early curve generation techniques.
My email is [email protected]
Many Thanks.
John.
Hi Arnold,
Admit I am very late in this forum. But much appreciate if you could send me the late and early curve generation techniques.
My email is [email protected]
Many Thanks.
John.
Hey all
Can you send detial as well??
Hey All
i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.
PERCENTAGE PHYSICAL PROGRESS CALCULATION?
Hey All
i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.
PERCENTAGE PHYSICAL PROGRESS CALCULATION?
Hey All
i NEED TO GENERATE FINANCIAL S-CURVE FROM P-6, HOW TO DO IT? CAN ANYONE EXPLAIN.
PERCENTAGE PHYSICAL PROGRESS CALCULATION?
hey
can you send me the steps for doing the early and the late cumaltive curves on P6,please send it to my email
[email protected] thanks
hey can you send me the steps of how i do the early and late cumaltive cash flow for cost and time for the whole project, please send me the steps at [email protected] thanks alot
Hi Arnold,
Please send it to me also
My email is: [email protected]
Thanks
Samer
Arnold,
Please send those details to me [email protected]
Regards,
Saule
Hi Arnold
Can you post your steps in this forum so that everybody can see
cuz the forum is full of email request
Thanks
Leo
Hi Mark,
Can you help me how to use Global change? Can you give me a procedure how to change duration % to physical % using global change...
Thanks.
Emee
Hi Mark,
Can you help me how to use Global change? Can you give me a procedure how to change duration % to physical % using global change...
Thanks.
Emee
Hi Arnold,
Please, also send me the steps on how to create the comulative late curve in P6.
This is my email :[email protected]
Thanks & Regards
Dindima.
this is a bit late for a request, please also send me this exercise.. thanks
i Appreciate if anyone send copy to me
[email protected]
i Appreciate if anyone send copy to me
[email protected]
i agree to the suggestion of Mr. Waheed Mirza.
just try it. it's easy.
more power Planners!
Hi Arnold & Others,
Can you please Send me the steps to be followed to create S- Curves for Both Early and Late dates.
My e-mail id is [email protected].
Thanks in advance
Olá Arnold
can you send me also
[email protected]
Thanks
Rabello from Brazil
Olá Arnold
can you send me also
[email protected]
Thanks
Rabello from Brazil
I did one just a couple of months ago. Note that your schedule should not have any updates yet. Then follow Karim Maghob's recommendation. It shoudn't be rocket science.
I did one just a couple of months ago. Note that your schedule should not have any updates yet. Then follow Karim Maghob's recommendation. It shoudn't be rocket science.
Pagination