Guys,
Already sent.
Hi Arnold,
Could you please send it to me in [email protected].
Cheers
Please, can you send me the steps to create early late curves in P6 to [email protected]?
Thank you
Already sent.
Arnold,
You missed me in the distibution list :(
Here is my mail address :
[email protected]
Gracias,
--
Afda
and me Please :
[email protected]
Guys,
Already sent.
Good day gentlemen,
I would also like to have the instructions in how to plot a late / early curve.
Thanks,
Brian
[email protected]
Hi Arnold,
Please,send me the steps on how to create the comulative late curve in P6.
my e-mail is:[email protected]
Sorry :) forgot to post my mail address :
[email protected]
Btw, Ive followed the instructions posted regarding this topic. But still need another enlighten advices to check if I am on the track.
Thanks guys !
Hi Arnold or other folks,
Please send me as well. I still dont understand how to generate s-vurve in P6
hi
can u send me also
[email protected]
regards
ATUL
Already sent.
I have not try this in P6 yet, but It should work.
If you make a copy of your current schedule and by using global change you constrain all your activities to be completed as late as possible, then all your resources will be allocated to the latest possible date.
I do not believe purely on early and late curves tho, probability of an schedule is the most important subject to asses if the early and late curves are healthy...
Hi Arnold,
Please, also send me the steps on how to create the comulative late curve in P6.
This is my e-mail.. [email protected].
Regards,
Edmar
Thanks a lot
Already sent.
Hi Arnold,
Can you send me also, this is my email [email protected]
Thanks
Hi Guys,
I already sent to your email. But please if you have something in detail try to share to others.
I know most of the Planners need your assistance. Its up to you to comments my WORK. But this is my initiatives & ideas on how to show the Early & Late Curve in P6.
Thank you.
Regards,
Arnold
Hi Arnold my email address is [email protected].
Please can you send me the steps on how to creat late curves.
Regards,
KZ
Hi Arnold
Can you please also post to me
[email protected]
Hi Mr Arnold
can you send me also
[email protected]
Thanks
Hi Arnold,
Im also following the steps, please continue and send to my email [email protected]
Tnx in advance,
Hi Arnold.
I have done the said steps. Can you please guide me what to do next or please send me steps to
[email protected]
Thanks
AK
my email is [email protected]. I think you have got it because i send you a subsea programme last year.
I also want to know about forcasting of man-hour.
Thanks
Hi KZ,
Pls. send me your email address and I will send you the steps.
Arnold
Go to the resource profile and right click then choose- Resource usage profile option in the Data section..
Choose Cost to display and also mark check box of remaining early & remaining late.
Then mark the resources in the left pane..youll find the graph for remaining early and late
Try to do this exersice and let us know the result
Arnold, Please can you show me how to generate the late curves from P6.
Thanks,
KZ
Hi Paul,
If you can do this in P3 you can also do this in P6. The same steps but different approach.
You must create two baselines in one project.
1. Baseline (Early Planned)
2. Late Planned
After creating these two, assign them. The first one as Project Baseline and the second one as Primary.
Try this and I will tell you what to do next.
Regards,
Arnold