Calendar is causing budget to change

Hello;

I am starting to add budgeted labor units to my schedule.  The activities have a duration type of "Fixed Duration and Units/Time.

I set up my resource id's and assigned them to the activities.  When I go to add the budgeted labor units of say 100 , the budgetd labor units column says 80.  When I look at the detail I see the electrician has 100 budgeted labor units.  

User Preferences are: 

Resource Anaysis Tab

Opened Projects Only

Remaining Early dates

Custom Role Limit

Calculations Tab:

Recalcutate the units...

Assignements are both set to ask

Project Settings are: Calculations

Link Budget at completion

Reset Remaining Durations and Units to Original

Subtract Actual from At Completion

Link Actual to date and actual this period units and cost.

I cannot find that this is a setting feature - the resource calander is a standard 5 day workweek - and I have created new calendars.   Is there a setting Im missing? 

 

 

Z
Zoltan Palffy 👤 Member for 17 years

this is based on your resource and what you have set for Default Units/Time if it is set to 8/d

then it takes 8*the duration and give the manhours 

so fo the duration is 10 days the 8*10= 80 manhours or units 

you can change them manually or do them all at once then export to excel change the manhours save it then import back into P6

D
david kelly 👤 Member for 10 years 5 months

A bit more detailed explanation please, Cynthia.

 

You add an actvity with what duration on what calendar

Then you add a resouirce assignmnet record, with a resource on what calendar

you add 100mhr into whiich field

Which budegeted labour units field (resource or activity) then says 80, or is it both

Featured Partner

Top Posters

Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts