Can't get P6 to assign Baseline dates

J
John Kelly 👤 Member for 14 years 11 months

Hi folks,

I searched the forums for an answer to this and couldn't find anything hence the new post.

I have multiple programmes, A baseline and monthly updates. 

I have assigned the monthly update of March as a baseline to the April update, (reason being i want to show alippage against previous month rather than against baseline)

I have added the baseline as usual using the 'maintain' function then assigned as Primary baseline, problem is though that the planned dates (BL1) aren't showing as the dates that i can see when i look at the March programme, i think its taking the dates from the original Baseline somehow.

 

Anybody any ideas?

 

Thanks in advance

R
Raymund de Laza 👤 Member for 16 years 7 months

John,

Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires.

Hope this will help.

Featured Partner

Top Posters

edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
James Williams
75 posts
Elyar Safarov
1 posts
Christopher Ganotice
1 posts
Ola Gbotoso
0 posts

Our Partners