Can't get P6 to assign Baseline dates

J
John Kelly 👤 Member for 14 years 10 months

Hi folks,

I searched the forums for an answer to this and couldn't find anything hence the new post.

I have multiple programmes, A baseline and monthly updates. 

I have assigned the monthly update of March as a baseline to the April update, (reason being i want to show alippage against previous month rather than against baseline)

I have added the baseline as usual using the 'maintain' function then assigned as Primary baseline, problem is though that the planned dates (BL1) aren't showing as the dates that i can see when i look at the March programme, i think its taking the dates from the original Baseline somehow.

 

Anybody any ideas?

 

Thanks in advance

R
Raymund de Laza 👤 Member for 16 years 6 months

John,

Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires.

Hope this will help.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts