Hi folks,
I searched the forums for an answer to this and couldn't find anything hence the new post.
I have multiple programmes, A baseline and monthly updates.
I have assigned the monthly update of March as a baseline to the April update, (reason being i want to show alippage against previous month rather than against baseline)
I have added the baseline as usual using the 'maintain' function then assigned as Primary baseline, problem is though that the planned dates (BL1) aren't showing as the dates that i can see when i look at the March programme, i think its taking the dates from the original Baseline somehow.
Anybody any ideas?
Thanks in advance
what columns are you displaying ?
After maintain baseline did you do assign baseline?
John,
A common issue, which Paul Harris has addressed very well is this presentation:
http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf
Cheers,
G
John,
Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires.
Hope this will help.