Hi All, Just asking on this situation regarding concurrency.Contractor's Delay from 30 Oct 2016 to 30 April 2017.Client's Delay from 30 Jun 2016 to 30 Mar 2017.Is it a concurrent delay? many thanks!

Z
Zoltan Palffy 👤 Member for 16 years 11 months

Contractor's Delay from 30 Oct 2016 to 30 April 2017

Client's Delay from 30 Jun 2016 to 30 Mar 2017.

Is it a concurrent delay?

if you hand draw this on paper it will be crystal clear
 
 There are 2 parts attributal to the contractor delays. The Contractor Delay #1 is from June 30, 2016 to October 29,2016. The concurrent portion of the delay is from October 30, 2016 to March 30, 2017. The Contractor Delay #2 is from April 1, 2017 to April 30, 2017
J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Hi Dimple,

Ya it is Concurrent delay.

 

So you can apply LD for a Duration of Contractor Finish Date - Client Delay Impact Date = 30 April 17 - 30 Mar 17 = 30 Days.

 

Mike would be able to answer it much better.

 

Regards

Jithin

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts