Hi All, Just asking on this situation regarding concurrency.Contractor's Delay from 30 Oct 2016 to 30 April 2017.Client's Delay from 30 Jun 2016 to 30 Mar 2017.Is it a concurrent delay? many thanks!
Hi All, Just asking on this situation regarding concurrency.Contractor's Delay from 30 Oct 2016 to 30 April 2017.Client's Delay from 30 Jun 2016 to 30 Mar 2017.Is it a concurrent delay? many thanks!
Contractor's Delay from 30 Oct 2016 to 30 April 2017
Client's Delay from 30 Jun 2016 to 30 Mar 2017.
Is it a concurrent delay?
Hi Dimple,
Ya it is Concurrent delay.
So you can apply LD for a Duration of Contractor Finish Date - Client Delay Impact Date = 30 April 17 - 30 Mar 17 = 30 Days.
Mike would be able to answer it much better.
Regards
Jithin