Multi Level Programme / Multiple Critical Path

H
Hermie LaO 👤 Member for 21 years 5 months
H
Hermie LaO 👤 Member for 21 years 5 months

Hi Brennan,



Website is www.welcom.com.



Yes Open Plan has entry level Earned Value capability. Full blown Earned Value system, with another product called COBRA(fully integrates with Open Plan).



Sub-programmes % Complete Rolls up to summary levels as well! However, it is a bit tricky with Budget quantities (since usually they are detailed at the bottom and then rolled-up). However there is a workaround. You can save the initial budget quantities to a different field. So when you roll-up % complete you can compare against that static(planned summary budget quantity).



Yes Open plan is a multi-user / multi-project system.



Regards!

B
Brennan Westworth 👤 Member for 23 years 5 months

sounds nice



can u post a link to the website?



I especially like the idea of these summary activity’s sub-programmes having a critical path.



It is important to know what is critical to the deliverable, but this may or may not be critical to the overall project. I can see many applications for this in my current work.



Does OP do Earned Value Analysis? it would be great if the sub-programme’s % complete automatically rolled up the the summary activity and could be applied to a budgeted quantity at this level.



Also... is there a multi user feature?

Featured Partner

Top Posters

Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts