Multi Level Programme / Multiple Critical Path

Member for

20 years 9 months

Hi Brennan,



Website is www.welcom.com.



Yes Open Plan has entry level Earned Value capability. Full blown Earned Value system, with another product called COBRA(fully integrates with Open Plan).



Sub-programmes % Complete Rolls up to summary levels as well! However, it is a bit tricky with Budget quantities (since usually they are detailed at the bottom and then rolled-up). However there is a workaround. You can save the initial budget quantities to a different field. So when you roll-up % complete you can compare against that static(planned summary budget quantity).



Yes Open plan is a multi-user / multi-project system.



Regards!

Member for

22 years 8 months

sounds nice



can u post a link to the website?



I especially like the idea of these summary activity’s sub-programmes having a critical path.



It is important to know what is critical to the deliverable, but this may or may not be critical to the overall project. I can see many applications for this in my current work.



Does OP do Earned Value Analysis? it would be great if the sub-programme’s % complete automatically rolled up the the summary activity and could be applied to a budgeted quantity at this level.



Also... is there a multi user feature?