Activity Delay in p6

Hi every one

can  Actrivitiy Has a delay in days more than the Updating interval ex.: if th update Int.=30days

after update can the activity has more than 30 days delay greater than the previous delay ???

R
Rafael Davila 👤 Member for 22 years 3 months

Reverse Logic might allow this to happen without using negative lag and without being OOS progress. Technically it cannot be OOS progress as it has not even progressed! Try it yourself.

 photo Reverse Logic_zpsk2j732ub.png

K
Kannan CP 👤 Member for 17 years 11 months

it is possible to have the activity starts before the completion of predecessor.It is out of sequence activity.

 

Regards

Kannan

A
Atif Mehmood 👤 Member for 9 years 8 months

Good afternoon all,

Is it possible, actual start date of activity earlier than his predecessors milestone.

Thanks.

A
Atif Mehmood 👤 Member for 9 years 8 months

Good afternoon all,

Is it possible, actual start date of activity earlier than his predecessors milestone.

Thanks.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

yes there are many ways. 1. The remaining durations along the critical are now greater than the previous update for whatever reason. 2. You have increased a duration because of a long lead time item deliver date has changed. 3. You made major logic changes which increased the total length of the critical path. 4. You are now working 5 days per week instead of 6 days per week. Of course all of these scenarios this work is or now is on the critical path. 6. you now have an earlier project must finish by date. 7. You inserted an start no earlier than date into your schedule which became critical. 8. You don't have enough resources and your resources are driving the durations. 9. Last month you overstated your progress and now you have to make some adjustment to your % complete which in turn increases your remaining durations.

T
Tom Boyle 👤 Member for 19 years 6 months

Haytham,

There is not much to improve on Robert Bell's answer to your initial question.  As to your follow-up question:

Absent any other changes, in P6, the early finish will be the Remaining Duration + Remaining Early Start.  For an in-progress activity, Remaining Early Start will be the same as Data Date unless it has been pushed out by retained logic (i.e. an unsatisfied predecessor) or some other constraint (including Suspend/Resume).  In either case you would easily see this, as the uncompleted part of the bar on the Gantt chart will move away to the right of the data date.

The task calendar may also have an increase in non-working time during the upcoming month (compared to last month).  This can make your early finish date later than you expect (but your expectation would have been wrong.)

Good luck, tom 

H
haytham saad 👤 Member for 13 years 1 month

Hi Robert

thnx for ur answer but beside these issue if i dont do any of them and no progress in the activity does the new finish date expected = remaing duration +Data date ??

R
Robert Bell 👤 Member for 9 years 11 months

Hi Haytham,

Sure activities can have greater delays than the update period. Changing the logic, adding constraints, or increasing remaining durations; any of these can lead to greater slips in a period than the period itself.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts