Updating a Program with 5,000 Activities

Member for

19 years 10 months

AMAR SOOGRIM

I am using the filter for two weeks lookahead in my P6v7,

Where, Start is "is within the range of" DD and DD+2 Weeks

And, Activity Status "not equals" Completed

What is the difference?

Cheers & Thanx

Tanveer

Member for

19 years 10 months

Hi SM

Alternatively you can invest in better software such as Asta Powerproject where you can copy and paste fron a spreadsheet directly into the progress column - job done in 10 secoonds.

Much cheaper than 2 assistants - and you toggle directly between P6 and Asta at any time.

Best regards

Mike Testro

Member for

13 years 10 months

Agreed you can filter out all ongoing activities as well as activities during the period to be updated and with the help of some assistant schedulers or meeting with the supervisors and collate information.

Member for

13 years 11 months

mukunda y

can you please tell me 2 weeks ahead filter.I normally apply this,

Where ,  Start is" Less than or Equal to" DD+2 Weeks

and Activity Status "equals"  In Progress.

 

Is it correct.Anybody else?

 

Regards,

Member for

17 years

In my exp updating is not a problem, it takes more time.

Problem is in that collecting the informationm, for that i would advise you to have 1 or 2 assistants.