Updating a Program with 5,000 Activities

S
SM PUM 👤 Member for 14 years 6 months

Hi All,

 

I have a programe with almost 5000 activities.No for a specific Period there are hundreds of activities going on.What is the best way to update such programs?

I am using Primaver P6

 

best Regards

T
Tanveer Ahmad Niazi 👤 Member for 20 years 5 months

AMAR SOOGRIM

I am using the filter for two weeks lookahead in my P6v7,

Where, Start is "is within the range of" DD and DD+2 Weeks

And, Activity Status "not equals" Completed

What is the difference?

Cheers & Thanx

Tanveer

M
Mike Testro 👤 Member for 20 years 5 months

Hi SM

Alternatively you can invest in better software such as Asta Powerproject where you can copy and paste fron a spreadsheet directly into the progress column - job done in 10 secoonds.

Much cheaper than 2 assistants - and you toggle directly between P6 and Asta at any time.

Best regards

Mike Testro

A
AMAR SOOGRIM 👤 Member for 14 years 5 months

Agreed you can filter out all ongoing activities as well as activities during the period to be updated and with the help of some assistant schedulers or meeting with the supervisors and collate information.

S
SM PUM 👤 Member for 14 years 6 months

mukunda y

can you please tell me 2 weeks ahead filter.I normally apply this,

Where ,  Start is" Less than or Equal to" DD+2 Weeks

and Activity Status "equals"  In Progress.

 

Is it correct.Anybody else?

 

Regards,

M
mukunda y 👤 Member for 17 years 6 months

In my exp updating is not a problem, it takes more time.

Problem is in that collecting the informationm, for that i would advise you to have 1 or 2 assistants.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts