P6 Activity Order and Sort Problem by "Start Date"

Z
Zoltan Palffy 👤 Member for 16 years 10 months

go to group and sort and group it as you want then on the right select sort then add the order there

J
Jordan Hansing 👤 Member for 9 years 11 months

I am having a similar issue.  I created my schedule and then later needed to add a new activity.  I've left room in the Activity ID's for the new activity to be in the desired corresponding order. The duration, start time and stop time are all identical to Activities A and B but no matter how I sort my activities the new activity is always 3rd in the sequence behind A and B.

V
Vasilios Sarras 👤 Member for 15 years 11 months

Cheers for this one Richard! Worked a treat, keep up the good work. 

Many thanks,

Vas

R
Richard Rowberry 👤 Member for 23 years 2 months

Greg,

 

A very old posting, but in the Group and Sort Field, you can apply multiple Sortings, to further filter the sorting criteria. In this scenario, firstly sort by Start Date ascending, and then a secondary sort by Finish Date ascending. This way whenever you have a Start Milestone and a Task starting on the same date, by default, the activity will finish later than the Milestone and appear below it

 

Regards

 

Richard Rowberry

R
Rodel Marasigan 👤 Member for 19 years 7 months

Greg,

By default Primavera used sorting field by unique field sequence number (which data ever created first). It means that if you created the task before the milestone then task will always above the milestone if both are sorted on the same field identifier.



Ex: Act1 = Task and Act2 = Milestone.

If Act2->FS-> Act1 then it will sort as task then milestone because milestone has zero duration and it will start on the same time (sorting field start).



You can create any sort field to solve this but I recommend using Activity ID and aligned the Activity ID to sort correctly. (Group & Sort: Start then Activity ID)

R
Rashid Iqbal 👤 Member for 16 years 2 months

Gary,



Try sorting out by Start date first and then Activity type...it should put the milestone above the activities even if starting the same day.



Or



Create a sort ’UDF’ auto fill it and then sort it the way you want to. It is not difficult even for 4000 activity schedules.



Regards




G
Gary Whitehead 👤 Member for 17 years 2 months

I’m no P6 expert either, but could you not just sort by start date and then by activity type?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Greg



Welcome to Planning Planet



Just a guess because I don’t use P6 - is the Link from the milestone SS or SF?



Best regards



Mike Testro

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts