I have seen the Video. That is for Task summry not for the Project summary. I can do also for the task summary but cannot for the project summary. If any other method you have please reply me
Thanks\\
KBJ
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Fri, 2011-02-18 12:40
please check how the 24h calendar is being applied in your project; I suspect this calendar was applied to subsidiary tasks (Task Information) and not to the project itself (Project Information)
Member for
14 years 8 monthsDear Rafael I have
Dear Rafael
I have seen the Video. That is for Task summry not for the Project summary. I can do also for the task summary but cannot for the project summary. If any other method you have please reply me
Thanks\\
KBJ
Member for
21 years 8 monthsYou
You can.
http://www.youtube.com/watch?v=-j4EwsDFXNs
Regards,
Rafael
Member for
14 years 8 monthsDear Rafael It is
Dear Rafael
It is the summary and not editable. please suggest how can i edit it.
Member for
21 years 8 monthsClick where you see None (at
Click where you see None (at Summary Task) and change it to 24 hrs calendar and let me know.
Member for
14 years 8 monthsDear Rafael In
Dear Rafael
In my project Calculation mode is automatic and calendar in Task information & project infromatin is same i.e 24 hous.
Regards\\
KBJ
[[wysiwyg_imageupload:238:]]
Member for
21 years 8 monthsWhere the calendars
Where the calendars different?
If different and you changed the calendar did you run a schedule run?
I use MS Project rarely but because use MS Project 2010 I setup all task mode in automatic.
Member for
14 years 8 monthsRafael It does not solve
Rafael
It does not solve my problem
KBJ
Member for
14 years 8 monthsRafael It does not solve
Rafael
It does not solve my problem
KBJ
Member for
21 years 8 monthsTry inserting a column to
Try inserting a column to display Task Calendar, if it differs at a Summary Bar change it to 24 hours and let us know what happened.
Member for
22 years 9 monthsWell, I don't know; do you
Well, I don't know; do you want to send me your project? I'll give you my email address in a private mesage
Alexandre
Member for
14 years 8 monthsDaer Alexandre
Daer Alexandre
Thanks for your reply. But i have assign in both fiel 24 hous calendar.
Kumar
Member for
14 years 8 monthsDaer Alexandre
Daer Alexandre
Thanks for your reply. But i have assign in both fiel 24 hous calendar.
Kumar
Member for
22 years 9 monthsHello Kumar,please check how
Hello Kumar,
please check how the 24h calendar is being applied in your project; I suspect this calendar was applied to subsidiary tasks (Task Information) and not to the project itself (Project Information)
Alexandre