Project Summary show only one fourth duration of activity

Member for

14 years 8 months

Dear Rafael

         I have seen the Video. That is for Task summry not for the Project summary. I can do also for the task summary but cannot for the project summary. If any other method you have please reply me

Thanks\\

KBJ

Member for

14 years 8 months

Dear Rafael

            It is the summary and not editable. please suggest how can i edit it.

Member for

21 years 8 months

Click where you see None (at Summary Task) and change it to 24 hrs calendar and let me know.

Member for

14 years 8 months

Dear Rafael

               In my project Calculation mode is automatic and calendar in Task information & project infromatin is same i.e 24 hous.

 

Regards\\

KBJ

[[wysiwyg_imageupload:238:]]

Member for

21 years 8 months

Where the calendars different?

If different and you changed the calendar did you run a schedule run?

I use MS Project rarely but because use MS Project 2010 I setup all task mode in automatic.

Member for

21 years 8 months

Try inserting a column to display Task Calendar, if it differs at a Summary Bar change it to 24 hours and let us know what happened.

Member for

22 years 9 months

Well, I don't know; do you want to send me your project? I'll give you my email address in a private mesage

Alexandre

Member for

14 years 8 months

Daer Alexandre

          Thanks for your reply. But i have assign in both fiel 24 hous calendar.

 

Kumar

Member for

14 years 8 months

Daer Alexandre

          Thanks for your reply. But i have assign in both fiel 24 hous calendar.

 

Kumar

Member for

22 years 9 months

Hello Kumar,

please check how the 24h calendar is being applied in your project; I suspect this calendar was applied to subsidiary tasks (Task Information) and not to the project itself (Project Information)

Alexandre