Project Summary show only one fourth duration of activity

K
Kumar Baiju 👤 Member for 15 years 5 months

Hi Alll

      I have one question about the actual duratin in MS project-2003. I am using 24 hous calander for my prject. when i updated my actual duration E.g. 10 hrs then in project summary it shows only 2.41 hrs. similiarlr when 20 hrs it appears 4.83. I cannot understand why in summary it comes only nearly one fourth duration

 

4.83 Hrs
2.41 Hrs

20 Hrs
10 Hrs

K
Kumar Baiju 👤 Member for 15 years 5 months

Dear Rafael

         I have seen the Video. That is for Task summry not for the Project summary. I can do also for the task summary but cannot for the project summary. If any other method you have please reply me

Thanks\\

KBJ

K
Kumar Baiju 👤 Member for 15 years 5 months

Dear Rafael

            It is the summary and not editable. please suggest how can i edit it.

R
Rafael Davila 👤 Member for 22 years 4 months

Click where you see None (at Summary Task) and change it to 24 hrs calendar and let me know.

K
Kumar Baiju 👤 Member for 15 years 5 months

Dear Rafael

               In my project Calculation mode is automatic and calendar in Task information & project infromatin is same i.e 24 hous.

 

Regards\\

KBJ

[[wysiwyg_imageupload:238:]]

R
Rafael Davila 👤 Member for 22 years 4 months

Where the calendars different?

If different and you changed the calendar did you run a schedule run?

I use MS Project rarely but because use MS Project 2010 I setup all task mode in automatic.

R
Rafael Davila 👤 Member for 22 years 4 months

Try inserting a column to display Task Calendar, if it differs at a Summary Bar change it to 24 hours and let us know what happened.

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Well, I don't know; do you want to send me your project? I'll give you my email address in a private mesage

Alexandre

K
Kumar Baiju 👤 Member for 15 years 5 months

Daer Alexandre

          Thanks for your reply. But i have assign in both fiel 24 hous calendar.

 

Kumar

K
Kumar Baiju 👤 Member for 15 years 5 months

Daer Alexandre

          Thanks for your reply. But i have assign in both fiel 24 hous calendar.

 

Kumar

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hello Kumar,

please check how the 24h calendar is being applied in your project; I suspect this calendar was applied to subsidiary tasks (Task Information) and not to the project itself (Project Information)

Alexandre

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts