Confusion in Negative Lag

I
Irfan Khan 👤 Member for 16 years 11 months

Hi to all,

 

I am scheduling for infrastructure project. I startd my Project from 01-07-2010 and finish date is 12-01-2011.

i linked each & every activities but i m unable to define critical path. at last my lag is coming (-1).

even i m finishing my project on 12-01-2011.

i dont know how is coming i am facing this problem 1st time.

pls give me any solution ..

 

thanks.....

N
niles luo 👤 Member for 20 years 6 months

hi,

   I think the reason is the same with "Maybe the “must finish” date is set up for early in the morning while projected finish is for the same date late in the evening."

  Pls confirm it by showing the hours of date.

Best Regards. 

I
Irfan Khan 👤 Member for 16 years 11 months

thanks for reply,

 

but i m changing date of must finish it is still showing minus lag (-1).

 

hv any other solution..

thanks.......

R
Rafael Davila 👤 Member for 22 years 3 months

Maybe the “must finish” date is set up for early in the morning while projected finish is for the same date late in the evening.

W
walid Lahiani 👤 Member for 15 years 7 months

hello

Dont worry khan,

you have to change the must finish date of the project

that's why I think the total float =-1

W
walid Lahiani 👤 Member for 15 years 7 months

hello

Dont worry khan,

you have to change the must finish date of the project

that's why I think the total float =-1

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts