Project End dates Changes when Importing
Forum Sponsor
Top Posters
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Amreshwar
Did you check the hours per day settings in the Admin preferences?
BTW if you have a maintenance contract its better to upgrade. Some bugs of version P6.0 (pre Oracle) became solved in P6.1.
Regards
Dieter
Dear Muhammad,
Thanks for the reply,
I have change the import configuration to the update existing" but no difference.
I think this may be due to some other setting , which I am not able to figure out this moment!!! May be due to different versions??????
Can any body help on this issue>>
Thanks.
Amreshwar,
The default setting in the import configuration option is keeping the existing calendars. It means if you have calendar with the same name as you are importing with XER then import will keep the existing calendar. what you need to do is to change the import configuration option for calendars to update existing
Hope this will solve the problem.
regards
Muhammad