I think the original post was asking about the P3 feature called the Datometer. No this is not in P3e. However as MKSE suggests make a request to Primavera Systems.
What I meant was that, when you move the cursor around the graphic area, we can see the date on the top correspond to the location of the graphic area, not physically stretching the bars.
You have noticed a difference between P3 and P3e. P3 early activity dates are automatically changed when you change the graphical bar manually.
The same type of thing holds true for P3e (but you didnt notice.) You think that the dates didnt change because the dates in the activity box didnt change. Here lies the difference.
With P3e, the graphical bar does not depict the activity early dates - it reflects the activitys planned dates. When you change the bar manually in P3e, you change the planned dates, not the early dates. Good luck!
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I think the original post was asking about the P3 feature called the Datometer. No this is not in P3e. However as MKSE suggests make a request to Primavera Systems.
Then this one is the wish list to Primavera.
Thanks Ron
What I meant was that, when you move the cursor around the graphic area, we can see the date on the top correspond to the location of the graphic area, not physically stretching the bars.
Cheers
Zubaidi
You have noticed a difference between P3 and P3e. P3 early activity dates are automatically changed when you change the graphical bar manually.
The same type of thing holds true for P3e (but you didnt notice.) You think that the dates didnt change because the dates in the activity box didnt change. Here lies the difference.
With P3e, the graphical bar does not depict the activity early dates - it reflects the activitys planned dates. When you change the bar manually in P3e, you change the planned dates, not the early dates. Good luck!
Ron Winter.
When you are stretching / compressing a bar graphically it shows, the dates and durations