date

F
Forum Guest 👤 Member for 17 years 4 months
J
Jim Fairchild 👤 Member for 23 years 3 months

I think the original post was asking about the P3 feature called the Datometer. No this is not in P3e. However as MKSE suggests make a request to Primavera Systems.

M
MK TSE 👤 Member for 24 years 3 months

Then this one is the wish list to Primavera.

F
Forum Guest 👤 Member for 17 years 4 months

Thanks Ron

What I meant was that, when you move the cursor around the graphic area, we can see the date on the top correspond to the location of the graphic area, not physically stretching the bars.



Cheers



Zubaidi

R
Ronald Winter 👤 Member for 23 years 5 months

You have noticed a difference between P3 and P3e. P3 early activity dates are automatically changed when you change the graphical bar manually.



The same type of thing holds true for P3e (but you didn’t notice.) You think that the dates didn’t change because the dates in the activity box didn’t change. Here lies the difference.



With P3e, the graphical bar does not depict the activity early dates - it reflects the activity’s planned dates. When you change the bar manually in P3e, you change the planned dates, not the early dates. Good luck!



Ron Winter.

M
MATHEW JOSEPH 👤 Member for 21 years 11 months

When you are stretching / compressing a bar graphically it shows, the dates and durations

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts