Hi Khuong,
I supposed you want to use the "automatic update" function and just suggesting to do it in your "baseline schedule".
If you use "automatic update" in your current schedule, that means you are progressing exactly as planned (which seldom or never happens, I guess?).
regards
Hi,
You need to show the Gantt Chart, if on top only show activity table then that option is grey out.
Regards.
Hi Anoon.
I afraid I cant understand your idea.
I login with administrator account.
Hi Duy.
My pleasure to know you.
My email : [email protected]
Regards
Hi Khuong,
I am Duy, vietnamese, working in Vung Tau City in a maritime group. I am also working on P6, and I really want to make friend with people who are working on P6 in Vietnam so if you feel OK, we can contact each other by email or mobile phone to discuss about P6.
My email: [email protected]
BR,
Duy (Mr)
Hi Khuong,
You must have the Apply Actuals project security privilege to update progress.
Regards,
Arnold
try doing it in your baseline schedule
Duy is right, but you have to show the Gantt Chart on top only.
Regards,
R. Catalan