Can not run Tool -> Update Progress

K
Khuong Do 👤 Member for 17 years 1 month
A
Anoon Iimos 👤 Member for 19 years 9 months

Hi Khuong,



I supposed you want to use the "automatic update" function and just suggesting to do it in your "baseline schedule".



If you use "automatic update" in your current schedule, that means you are progressing exactly as planned (which seldom or never happens, I guess?).



regards

D
Duy Huynh 👤 Member for 18 years 2 months

Hi,



You need to show the Gantt Chart, if on top only show activity table then that option is grey out.



Regards.

K
Khuong Do 👤 Member for 17 years 1 month

Hi Anoon.

I afraid I can’t understand your idea.



I login with administrator account.

D
Duy Pham 👤 Member for 17 years 1 month

Hi Khuong,



I am Duy, vietnamese, working in Vung Tau City in a maritime group. I am also working on P6, and I really want to make friend with people who are working on P6 in Vietnam so if you feel OK, we can contact each other by email or mobile phone to discuss about P6.



My email: [email protected]



BR,



Duy (Mr)

A
Arnold Puy 👤 Member for 19 years 2 months

Hi Khuong,



You must have the Apply Actuals project security privilege to update progress.



Regards,



Arnold

R
R. Catalan 👤 Member for 20 years 11 months

Duy is right, but you have to show the Gantt Chart on top only.



Regards,

R. Catalan

Featured Partner

Top Posters

Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts