the dates that you have now (jab and feb) could be the current forecasted dates while the units could be distributed according to the baseline dates?....
Try looking at your Planned Start and Planned Finish - the start and finish dates for the resource spread will be picked up from these fields - these dates may be different from your start and finish dates
Relationships are straight forward and do not seem to have an effect. And there are no constraints.
Tried different scenarios, changing to Fixed Duration and units with Physical % complete, or even Fixed duration and Units/time with duration, it does not seem to make a difference with the units and which period of time they are allocated. The resource profile settings have not been changed, but then not sure what they are supposed to be...only have a rate and thats that!
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Catherine,
the dates that you have now (jab and feb) could be the current forecasted dates while the units could be distributed according to the baseline dates?....
Thank you people!
Am currently trying the different solutions you guys suggested.
Thanks for your help.
Hi Catherine,
Try looking at your Planned Start and Planned Finish - the start and finish dates for the resource spread will be picked up from these fields - these dates may be different from your start and finish dates
Rgds
Richard
Hi!
Relationships are straight forward and do not seem to have an effect. And there are no constraints.
Tried different scenarios, changing to Fixed Duration and units with Physical % complete, or even Fixed duration and Units/time with duration, it does not seem to make a difference with the units and which period of time they are allocated. The resource profile settings have not been changed, but then not sure what they are supposed to be...only have a rate and thats that!
Hi Catherine,
did you check the relationships or any constraints or the resources profile settings.
wondering what different options you have tried??? lets share, we could advice you are on the correct path.
regards
Waseem Saber