Duration Type/% complete type

M
Mohamed elnenaei 👤 Member for 18 years 6 months

Dear Catherine,



the dates that you have now (jab and feb) could be the current forecasted dates while the units could be distributed according to the baseline dates?....

R
Richard Rowberry 👤 Member for 23 years 3 months

Hi Catherine,



Try looking at your Planned Start and Planned Finish - the start and finish dates for the resource spread will be picked up from these fields - these dates may be different from your start and finish dates



Rgds



Richard

C
Catherine Barthelemy 👤 Member for 18 years

Hi!



Relationships are straight forward and do not seem to have an effect. And there are no constraints.

Tried different scenarios, changing to Fixed Duration and units with Physical % complete, or even Fixed duration and Units/time with duration, it does not seem to make a difference with the units and which period of time they are allocated. The resource profile settings have not been changed, but then not sure what they are supposed to be...only have a rate and that’s that!

W
Waseem Saber 👤 Member for 21 years 7 months

Hi Catherine,



did you check the relationships or any constraints or the resources profile settings.



wondering what different options you have tried??? lets share, we could advice you are on the correct path.



regards



Waseem Saber

Forum Sponsor

Top Posters

J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts