Decimals in Total Float - P6 - why?

T
Terry Barber 👤 Member for 19 years

1 of your activity’s is starting or finishing at ???.10 You need to find it and i assume that you have a few activity’s that have this + 000’10 time period. You need to find the top activity that has this time period and when corrected it will cascade down through your programme and correct them all.

C
Christopher Nicolas 👤 Member for 20 years 2 months

Paul - none of the durations contain decimal points and the calendar is a standard 10 hour day, 6 day week. I am trying to figure it out??

P
Paul Harris 👤 Member for 25 years 3 months

Have you checked the calendar finish times or activity durations, something is probably not matching.





Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

Featured Partner

Top Posters

Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts
markg
0 posts
Manjeet Yadav
0 posts
Pan
0 posts
Tijo Kurian
11 posts
Zainab El-Beialy
3 posts