Decimals in Total Float - P6 - why?
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
1 of your activitys is starting or finishing at ???.10 You need to find it and i assume that you have a few activitys that have this + 00010 time period. You need to find the top activity that has this time period and when corrected it will cascade down through your programme and correct them all.
Paul - none of the durations contain decimal points and the calendar is a standard 10 hour day, 6 day week. I am trying to figure it out??
Have you checked the calendar finish times or activity durations, something is probably not matching.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au