How to export S-curve data to excel???

S
Sahar Khoshsirat 👤 Member for 14 years 11 months

Weighted steps in primavera plan P6

 

Hello

Does any body know how weighted steps can affect my plan?

Lets assume one activity has 4 steps, every step has its own start, finish and weight.

I would like to schedule the plan and draw plan Scurve, but the weights and dates in steps does not affect my %schedule.

Any help appreciated.

 

Sahar

A
A D 👤 Member for 19 years 2 months

Hi Johar,



U can try Pervasive ODBC drivers as well.



I have never used P5, but works brilliantly on P3.1



You dont need to perform these things with every update.



If u use pervasive ODBC drivers (Free download available on net) then u need to just press the REFRESH button and it will be updated.



Its far easy comapred to these things.



Paper for the same can be found at Paul Harris (www.eh.com.au) website



Cheers,



Ravi

J
johar Mishra 👤 Member for 18 years 5 months

Hi Mouneer,

Thanks a lot for your help. I tried all options and got a lot of new points there, but I couldn’t find axact descriptions you told (remainning early units)!

Could you please help me to find out this figure.



Please have my e-mail as below: [email protected]

M
Mouneer Adel 👤 Member for 20 years 11 months

Hi there



Open Reports and make a new report and choose time distrbuted data then activity resource assignments and then filter your required resources and when it comes to the time interval fields choose remainning early units & remaining late units , run report with the following options : ascii filed delimiter :tab text qualifier: none and choose the file name with xls extension and enjoy



I hope that helps you



Mouneer Adel

Featured Partner

Top Posters

Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts
Sunchana Johnston
12 posts
Akram Hammam Mohamed
17 posts
Sagar Raut
14 posts
Patricio_aoa
0 posts
James Williams
75 posts
Philip Assou-Dodji
1 posts
jeoffrey reyes
15 posts
markg
0 posts