Updating P5

T
Tomas Rivera 👤 Member for 25 years 2 months

Sandy:



The only fields I update are start and finish dates and activity percent complete. I do it all 3 in one import session and it works fine except for the ocasional errors in the percent complete as I mentioned before.



Do you have to do the import of activity percent complete after doing the import of dates for the percent complete to come up right?



Tomas Rivera

S
Sandy Matheson 👤 Member for 21 years 9 months

Thanks Tomas, that worked. But still a painfull process to update progress, this import/export is tedious. Why can we not update all required fields with one file import!!

Sandy

T
Tomas Rivera 👤 Member for 25 years 2 months

Sandy:



I have had the same problem as you have.

According to Primavera, you need to update the Activity % Complete field in your Excel file. Then when importing, the scheduler will update the corresponding % complete field depending on the % complete type you have configured for each activity.

But I still get the same problem again sometimes. So I am not sure what is going on.



Hope it helps



Tomas Rivera

Featured Partner

Top Posters

James Williams
75 posts
Alex Lyaschenko
26 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
Elyar Safarov
1 posts

Our Partners