Updating P5

T
Tomas Rivera 👤 Member for 25 years 1 month

Sandy:



The only fields I update are start and finish dates and activity percent complete. I do it all 3 in one import session and it works fine except for the ocasional errors in the percent complete as I mentioned before.



Do you have to do the import of activity percent complete after doing the import of dates for the percent complete to come up right?



Tomas Rivera

S
Sandy Matheson 👤 Member for 21 years 8 months

Thanks Tomas, that worked. But still a painfull process to update progress, this import/export is tedious. Why can we not update all required fields with one file import!!

Sandy

T
Tomas Rivera 👤 Member for 25 years 1 month

Sandy:



I have had the same problem as you have.

According to Primavera, you need to update the Activity % Complete field in your Excel file. Then when importing, the scheduler will update the corresponding % complete field depending on the % complete type you have configured for each activity.

But I still get the same problem again sometimes. So I am not sure what is going on.



Hope it helps



Tomas Rivera

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts