2. No need for making the activities independent or meeting.
The above functions are only needed when we want the reosurces to use their own specific calenders and want the crunching and stretching of the activties.
The only thing which you would be missing is to include the resources in the levelling dialog box.
There are few things you need to do for P3 to reschedule for a future date, an activity whose resource is not immediately available.
In addition to defining the resource limits and designating the resource as driving, you also need to select independent or meeting as the activity type. These selections will make P3 to recognize that the resource Calendar should be used in scheduling the activity and not the base calendar.
You also need to define the resource availability using the resource calendar (go to ‘Data’>> ‘Resources’ >> ‘Calendars’).
In leveling, P3 uses the combination of all these parameter to reschedule an activity whose resource is not available.
In summary try these steps:
1. Define the resource and resource availability using the resource calendar (go to ‘Data’>> ‘Resources’ >> ‘Calendars’).
2. Defining the resource limits
3. Designating the resource as driving
4. Choose independent or meeting as the activity type (if you select task as activity type, the base calendar will be used when leveling)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
For resource levelling there is no need to
1. Make the resources Driving
2. No need for making the activities independent or meeting.
The above functions are only needed when we want the reosurces to use their own specific calenders and want the crunching and stretching of the activties.
The only thing which you would be missing is to include the resources in the levelling dialog box.
Rashid
Hi all,
do not forget to select the resources you want to level in the Level, Resources dialog
if you do not know WHICH resource is overloaded, select ALL resources
P3 will not level resources not selected here
Good luck,
Alexandre
There are few things you need to do for P3 to reschedule for a future date, an activity whose resource is not immediately available.
In addition to defining the resource limits and designating the resource as driving, you also need to select independent or meeting as the activity type. These selections will make P3 to recognize that the resource Calendar should be used in scheduling the activity and not the base calendar.
You also need to define the resource availability using the resource calendar (go to ‘Data’>> ‘Resources’ >> ‘Calendars’).
In leveling, P3 uses the combination of all these parameter to reschedule an activity whose resource is not available.
In summary try these steps:
1. Define the resource and resource availability using the resource calendar (go to ‘Data’>> ‘Resources’ >> ‘Calendars’).
2. Defining the resource limits
3. Designating the resource as driving
4. Choose independent or meeting as the activity type (if you select task as activity type, the base calendar will be used when leveling)
I am optimistic it would work.
Akin Adurosakin
Nigeria
Fro memory as I dont use Resources that often, I think you have to define the resource as a driving resource. Is this the case?