V5 : Copying Actvities of one project to other

A
Amar Aghana 👤 Member for 20 years 11 months
H
Henk van der Heide 👤 Member for 21 years 11 months

Open both projects, the one you want to copy from and the one you want to paste to.

Organize bij WBS, select the activities, copy, and past within the WBS of the new project.

You can also paste in the same project, now you have the activities double, and change the WBS of the copied activities



Because P3e is full multiproject you’ve to difine the wbs for each activity. When you dont use WBS it puts all activities in the same project (what’s a part of the WBS)





regards,



Henk

W
Wilmore Makonese 👤 Member for 20 years 10 months

I would suggest exporting the project( or activities ) you want and then importing it/them in the project you want it/them to be.

M
Marcio Sampaio 👤 Member for 20 years 8 months

Dear all;



This forum is for P3e users. We have another forum for P3 users.



Using this one to discuss about P3 cause confusion.



Best regards.



Marcio Eduardo.

A
Alex Wong 👤 Member for 23 years 5 months

MUHAMMAD



It is P3e not P3 therefore there is no such thing as fragnet.



Cheers



Alex


A
Amar Aghana 👤 Member for 20 years 11 months

Alex, Thank you.



Thanks to all for participation.



Cheers, Amar.

A
Alex Wong 👤 Member for 23 years 5 months

Thats right becasue the software need to know which Node (EPS) you want to paste the activity that why you either group by "EPS/WBS" or Just "WBS"



Alex

A
Amar Aghana 👤 Member for 20 years 11 months

Alex,



I have projects structured by activity codes not by WBS. When I open two projects and try to paste, it could not be done.



However, by default, WBS Level 1 is project itself. I grouped two projects by WBS for Level 1 and then tried. It worked out!

A
Alex Wong 👤 Member for 23 years 5 months

Amar



If you copy the activities in one project first, open both and organise it by EPS/WBS. Then you can select them and drop it into the project you wand to paste. Make sure you have rights to both projects.



HTH



Alex

S
Shah Shams Alam 👤 Member for 20 years 11 months

Select both the projects in Entrprise breakdown structure using controll key. Right click and open, Both the projects will open. Now u can copy and paste.

H
Harold Martin 👤 Member for 20 years 9 months



Muhammad,



Highlight the activities you want to copy go to tools fragnet, store fragnet put ID & title, then open other project go to fragnet, retrieve fragnet than select.



kind regards,



Harold

infrastructure/tower projs.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts