Open both projects, the one you want to copy from and the one you want to paste to.
Organize bij WBS, select the activities, copy, and past within the WBS of the new project.
You can also paste in the same project, now you have the activities double, and change the WBS of the copied activities
Because P3e is full multiproject youve to difine the wbs for each activity. When you dont use WBS it puts all activities in the same project (whats a part of the WBS)
If you copy the activities in one project first, open both and organise it by EPS/WBS. Then you can select them and drop it into the project you wand to paste. Make sure you have rights to both projects.
Select both the projects in Entrprise breakdown structure using controll key. Right click and open, Both the projects will open. Now u can copy and paste.
Highlight the activities you want to copy go to tools fragnet, store fragnet put ID & title, then open other project go to fragnet, retrieve fragnet than select.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Open both projects, the one you want to copy from and the one you want to paste to.
Organize bij WBS, select the activities, copy, and past within the WBS of the new project.
You can also paste in the same project, now you have the activities double, and change the WBS of the copied activities
Because P3e is full multiproject youve to difine the wbs for each activity. When you dont use WBS it puts all activities in the same project (whats a part of the WBS)
regards,
Henk
I would suggest exporting the project( or activities ) you want and then importing it/them in the project you want it/them to be.
Dear all;
This forum is for P3e users. We have another forum for P3 users.
Using this one to discuss about P3 cause confusion.
Best regards.
Marcio Eduardo.
What!!??
MUHAMMAD
It is P3e not P3 therefore there is no such thing as fragnet.
Cheers
Alex
hi
guys
why not u using "fragnent"
Alex, Thank you.
Thanks to all for participation.
Cheers, Amar.
Thats right becasue the software need to know which Node (EPS) you want to paste the activity that why you either group by "EPS/WBS" or Just "WBS"
Alex
Alex,
I have projects structured by activity codes not by WBS. When I open two projects and try to paste, it could not be done.
However, by default, WBS Level 1 is project itself. I grouped two projects by WBS for Level 1 and then tried. It worked out!
Amar
If you copy the activities in one project first, open both and organise it by EPS/WBS. Then you can select them and drop it into the project you wand to paste. Make sure you have rights to both projects.
HTH
Alex
Select both the projects in Entrprise breakdown structure using controll key. Right click and open, Both the projects will open. Now u can copy and paste.
Open both projects. Than copy and paste.
Muhammad,
Highlight the activities you want to copy go to tools fragnet, store fragnet put ID & title, then open other project go to fragnet, retrieve fragnet than select.
kind regards,
Harold
infrastructure/tower projs.