My existing project has a project start date of April 05 and a project finish date of March06. I have now added in activities for April 06. These activities are showing critical. My guess is that this is due to the project finish date.
I figured if I could change the project finish date it would sort out the activities that are showing critical.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Glad to help.
Thank You very much for your guidance. I finally worked out what you meant.
I dont have that option.
If I click on PROJECT-
Activities
Resource Assignments
WBS
______________
Baseline
Expenses
Work Products and Documents
______________
Threshold
Issues
Risks
_______________
Set Default Project
Ok Mario,
Go on PROJECT view > DATES > and change MUST FINISH BY.
Hope it can help u.
Best regards,
Marcio Eduardo.
Rio de Janeiro - Brazil.
My existing project has a project start date of April 05 and a project finish date of March06. I have now added in activities for April 06. These activities are showing critical. My guess is that this is due to the project finish date.
I figured if I could change the project finish date it would sort out the activities that are showing critical.
Sorry Mario,
I cant understand what are u trying to do.
Do u have a timeschedule with 1 year durarion and whant to become it 2 years durarion, ok??
Does this timeschedule has any progress? Or it didnt start yet?
Probably u will have to change activity durations to achive 2 years, or detail more WBS inserting more activities etc.
My first impression is that u are replanning your project. Is that ok??
Regards.
Marcio Eduardo.