Changing the Projects Time Period
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Glad to help.
Thank You very much for your guidance. I finally worked out what you meant.
I dont have that option.
If I click on PROJECT-
Activities
Resource Assignments
WBS
______________
Baseline
Expenses
Work Products and Documents
______________
Threshold
Issues
Risks
_______________
Set Default Project
Ok Mario,
Go on PROJECT view > DATES > and change MUST FINISH BY.
Hope it can help u.
Best regards,
Marcio Eduardo.
Rio de Janeiro - Brazil.
My existing project has a project start date of April 05 and a project finish date of March06. I have now added in activities for April 06. These activities are showing critical. My guess is that this is due to the project finish date.
I figured if I could change the project finish date it would sort out the activities that are showing critical.
Sorry Mario,
I cant understand what are u trying to do.
Do u have a timeschedule with 1 year durarion and whant to become it 2 years durarion, ok??
Does this timeschedule has any progress? Or it didnt start yet?
Probably u will have to change activity durations to achive 2 years, or detail more WBS inserting more activities etc.
My first impression is that u are replanning your project. Is that ok??
Regards.
Marcio Eduardo.