Parsons Brinckerhoff Limited Project Controls Manager

Corporate Role: Head of Discipline - Project Management & Controls



PM&C best practice, careers and mentoring. PM&C input on various bids. Identification of issue and opportunities for PM&C, development of PM&C strategy and plan, creation of PM&C discipline working groups and project controls career path, introduction of standardised earned value project management techniques, scheduling structures and practices.



Project Role: Senior Consultant / Project Manager / Project Controls Manager

Parsons International Limited Forensic Planner

A
Amit Kumar 👤 Member for 19 years 9 months

This company is involved in PMC for Construction of 70 Kms of Light Rail Transport system in Dubai (in two phases of 52 Kms & 18 Kms).

Reporting to the Project Controls Manager, I was responsible for following



     Review, comment and recommend approval of the Project Baselines & subsequent programme revisions / cyclic progress programme updates.

     Preparation, validation and calculation of Monthly Project Earned Value for certification of Monthly Progress Payment Request and progress updates.

Afcons Infrastructure Limited Planning Manager

A
Amit Kumar 👤 Member for 19 years 9 months

This company was involved in Construction of 7 Kms of Viaduct & Two Station Buildings for Delhi Mass Rail Transport System in New Delhi

Reporting to the Project Manager, I was responsible for the following



     Prepare the monthly programme updates for the project

     Tracking progress, man hours and cost as compared to original plan and co-ordinate the weekly, fortnightly and monthly reports to Engineer / Employer

     Raise monthly payment request / invoices to the Engineer / Employer

Gammon India Limited Senior Planner

A
Amit Kumar 👤 Member for 19 years 9 months

This company was involved in Construction of 14 Kms of Viaduct for Delhi Mass Rail Transport System in New Delhi

Reporting to the Project Manager, I was responsible for the following



     Prepare the Base Line & subsequent revision/update of the program

     Tracking progress, man hours and cost as compared to original plan and co-ordinate the weekly, fortnightly and monthly reports to Engineer / Employer

     Raise monthly payment request / invoices to the Engineer / Employer