Railway
PCNL Planner
Current Role
Parsons Brinckerhoff Limited Project Controls Manager
Corporate Role: Head of Discipline - Project Management & Controls
PM&C best practice, careers and mentoring. PM&C input on various bids. Identification of issue and opportunities for PM&C, development of PM&C strategy and plan, creation of PM&C discipline working groups and project controls career path, introduction of standardised earned value project management techniques, scheduling structures and practices.
Project Role: Senior Consultant / Project Manager / Project Controls Manager
Jarvis Rail Planner
Current Role
Parsons International Limited Forensic Planner
This company is involved in PMC for Construction of 70 Kms of Light Rail Transport system in Dubai (in two phases of 52 Kms & 18 Kms).
Reporting to the Project Controls Manager, I was responsible for following
Review, comment and recommend approval of the Project Baselines & subsequent programme revisions / cyclic progress programme updates.
Preparation, validation and calculation of Monthly Project Earned Value for certification of Monthly Progress Payment Request and progress updates.
Afcons Infrastructure Limited Planning Manager
This company was involved in Construction of 7 Kms of Viaduct & Two Station Buildings for Delhi Mass Rail Transport System in New Delhi
Reporting to the Project Manager, I was responsible for the following
Prepare the monthly programme updates for the project
Tracking progress, man hours and cost as compared to original plan and co-ordinate the weekly, fortnightly and monthly reports to Engineer / Employer
Raise monthly payment request / invoices to the Engineer / Employer
MMC-Gamuda Joint Venture Sdn Bhd Lead Planner
Planning Analyst for Double Track Electrified Project covering total of 321 km stretch form Ipoh to Pedang Besar.
Gammon India Limited Senior Planner
This company was involved in Construction of 14 Kms of Viaduct for Delhi Mass Rail Transport System in New Delhi
Reporting to the Project Manager, I was responsible for the following
Prepare the Base Line & subsequent revision/update of the program
Tracking progress, man hours and cost as compared to original plan and co-ordinate the weekly, fortnightly and monthly reports to Engineer / Employer
Raise monthly payment request / invoices to the Engineer / Employer
Maeda Corporation Planning Manager
Contractor role - two design & build contracts (alternative bid) - KCRC West Rail, CC201 & CC211 viaducts (approx 24km)