This company is involved in PMC for Construction of 70 Kms of Light Rail Transport system in Dubai (in two phases of 52 Kms & 18 Kms).

Reporting to the Project Controls Manager, I was responsible for following



     Review, comment and recommend approval of the Project Baselines & subsequent programme revisions / cyclic progress programme updates.

     Preparation, validation and calculation of Monthly Project Earned Value for certification of Monthly Progress Payment Request and progress updates.

     Tracking progress, providing forecasts, areas of concern, what-if analysis.

     Monitoring progress, man hours, cost, budget and interfaces as compared to schedule. Managing Key Performance Indicator regime.

     Manage, prepare and provide progress forecast for Civil, Trackwork and Rail Systems works and Project Interfaces

     Review of Variation/Claim Items within Agreement and their incorporation and integration/budget loading into the baseline and working programme.

     Management of Project Programme Interface Schedule, providing forecast of slippage and areas of concern and management reporting of uncertainties.

     Provide feedback to management regarding staffing requirements based on changes to project schedules and resource / manpower loadings.

     Advising management of adverse schedule impacts, man hours and cost variations and the preparation of Interface Progress Schedules/spreadsheets.

     Perform Forensic Analysis (using Contemporaneous Schedule Analysis technique), Review periodic programme changes & their subsequent impact on the project completion and maintain Master Programme Change Register