Cost and Schedule Engineer, Parsons Corporation, Chevron Gas Processing Pascagoula Refinery

J
Julie Owen 👤 Member for 11 years 5 months
START Date
END Date
Experience Hours (Planning & Scheduling)
3200
Experience Hours (Cost Management)
3200

Worked as a Cost and Schedule Engineer on a gas processing facility, valued at $26M.  Prepared monthly cost forecast and maintained project cash flow for Chevron Magnolia Plant.  Forecasted and reported commitments and expenditures for engineering, equipment and bulk materials.  Processed client and home office change requests, tracked man-hours and compiled manpower curves.

3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date
Experience Hours (Planning & Scheduling)
100
Experience Hours (Cost Management)
150

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

Vaibhav Paydelwar

First Name
Vaibhav
Last Name
Paydelwar
Professional Since
Oldest experience
Years Experience
1
LinkedIn Profile
www.linkedin.com.vaibhavpaydelwar
Facebook Profile
www.facebook.com.vaibhavpaydelwar

A Qualified Mechanical Engineering Graduate offering 3+ years of experience in the areas of

  • Boiler Pressure Part Erection & Alignment
  • Boiler Structure including Primary & Secondary Structure
  • Air Preheater (Rotary Part)
  • Welding Inspection
  • Project Planning & Control

3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date
Experience Hours (Planning & Scheduling)
100
Experience Hours (Cost Management)
150

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date
Experience Hours (Planning & Scheduling)
100
Experience Hours (Cost Management)
150

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

Muhammad Mohsin

First Name
Muhammad
Last Name
Mohsin
Professional Since
Years Experience
0
Telephone Number
00923456464606
LinkedIn Profile
https://www.linkedin.com/in/muhammad-mohsin-pmp-7018bb52?trk=nav_responsive_tab_profile

Alejandra Marin Tabacco

First Name
Alejandra
Last Name
Marin Tabacco
Professional Since
Oldest experience
Years Experience
4

         Control and Project Planning  

Time and resources control & scheduling with software as Ms Project and Primavera P6 (updating project status), Collecting and analyzing field survey information, Evaluation of the project profitability, budget control, supply analysis, Expertise in cost control with methodologies as "Direct Costing", "Process Costing" and "Activity Based Costing", Risks & Constraints control, Project reassessment, Reporting for the General Direction.