Oil / Gas / Power

Planner/Scheduler, Petrosea, Oil & Gas Projects

START Date
END Date

o     create, update, maintain and control schedule in Primavera 3.1 and its impact on cost and resource
o     create progress reports
o     identify change orders, additional works and claims
o     progress claims (Invoicing)
o     subcontractor and resource management
Projects:
o     APN Development (BP West Java)
o     Attaka F/FS Offshore Platform Reconfiguration (Unocal Balikpapan)
o &

Senior Planning Engineer, Conoco Phillips Indonesia, Oil & Gas Projects

START Date

Work Description:
-       Establishing and monitoring programmes and reporting systems.

-       Critical path and float analysis

-       Risk assessment using PertMaster

-       Preparing progress reports including resources, histograms, S-curves, and Earned Value

-       Liaising with vendors, sub-contractors and other stakeholders

Projects: Dayung Compression and Grissik De-bottleneck

Project Control Engineer, PT. Rekayasa Industri, Power Generation

START Date
END Date

Work Description:
o     Update, maintain and control schedule in Primavera 3.1 and its impact on cost and resource
o     Progress Reports, weekly and monthly
o     Progress Claims (Invoicing)
EPC Total Project Kamojang 1x60MW
PT Pertamina Geothermal Energy
Value: USD 43,700,000.00 and IDR 154,476,432,000.00

Consolidated Contractors International Co -Qatar Planner

CCIC – QATAR - RAS LAFFAN ONSHORE EXPANSION PROJECT (LNG PLANT TRAINS)

REPORTING TO: Planning Manager

•     Progress Assessment/Quantity Analysis every week compared with Client’s Targets

     Civil, Building, Struc. Steel, Equipments, Piping prefab/install’n, Elect / Instrument

     Hydro testing, Insulation, Painting as well as fireproofing.

TOLEDO-Abu Dhabi Planner

TOLEDO – Abu Dhabi – GASCO RUWAIS RELOCATION OF SERVICES PROJECT

REPORTING TO: Project Manager

GASCO PROJECTS- Relocation of Utility Lines AND Demolition of Alkali wash units

•     Construction Schedule level 3 in M.S.Project 2003 / Primavera P3.1

•     Daily, Weekly, Monthly Progress Reports with S’ curves in Excel

•     Weekly progress meetings with Client.