TOLEDO-Abu Dhabi Planner

TOLEDO – Abu Dhabi – GASCO RUWAIS RELOCATION OF SERVICES PROJECT

REPORTING TO: Project Manager

GASCO PROJECTS- Relocation of Utility Lines AND Demolition of Alkali wash units

•     Construction Schedule level 3 in M.S.Project 2003 / Primavera P3.1

•     Daily, Weekly, Monthly Progress Reports with S’ curves in Excel

•     Weekly progress meetings with Client.