Presenting critical path when planned completion is prior to contractual completion
If planned completion date of a project is prior to contractual completion date, how would you most correctly show the critical path throughout the project?
Say the contractual duration of a project is 24 months and you plan to complete the project in 21 months, i.e. 3 months before, and you show this in the submitted programme.