Presenting critical path when planned completion is prior to contractual completion

B
Bo Johnsen 👤 Member for 20 years 4 months

If planned completion date of a project is prior to contractual completion date, how would you most correctly show the critical path throughout the project?

Say the contractual duration of a project is 24 months and you plan to complete the project in 21 months, i.e. 3 months before, and you show this in the submitted programme.

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Necking of Bars and Print Preview

I am using P6 v7 and have suspended some activities. 

I am trying to show the non work period on my layout, but when I chose bar necking it appears on my screen but as soon as I go to Print preview or print it’s gone.

I have checked my Timescale and Bars.

how I can solve this?

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

how to measure project performance ie physical progress using earned value s curve

R
RAO RAO 👤 Member for 17 years 8 months

Dear planners,

I need this very urgent please.i developed a project using p6.uploaded cost to the activites not all.based on that i developed s curve cash flow.this can be used for cost analysis.but how to measure physical progress of the project.because cost cant be used for progress measurement.can i use activity days as weigtage to all acitivites and develop s curve.

Regards,

rao

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Hill International is hosting seminars nationally this March in Australia on Extension of Time and Delay Analysis

H
Henry Sell 👤 Member for 19 years 9 months

Hill International is hosting seminars nationally this March in Australia on Extension of Time and Delay Analysis. To book, please call Niolas Lagier on 02 9241 7328 or visist www.hillintl.com.au
 

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Building contractor's Planning job Offer vs Energy sector Planning Offer

K
kamran shah 👤 Member for 15 years 4 months

I've received 2 different offers for a planning role one is with building contractors for one year fixed term contract and the other one is with well known energy sector company as a permanant planning role..... i m really confused which one should i accept... need your help ... got 4 years building planning experience... 

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Project logging software for Project management tools

G
Gary Fen 👤 Member for 15 years 4 months

Hi,

I’m a software developer and I’ve just developed a range of time planning / logging software using a timeline as the visual interface.

When the software is used for Project management style planning, the timing plan can be structured into a number of easy to manage layers and data, such as reports, meeting minutes, text, images, video clip etc can be save directly back to the plan.

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Gantt Chart Activity

A
Ammar Abbas 👤 Member for 15 years 4 months

I am a beginner at primavera, i need to know how one can change gantt chart to show one day activity occupying the whole duration, like in this example activity starts somewhere mind sunday and ends in mid Thursday, where as I want it to start from the end of Saturday (start of Sunday) and continue till the end of Thursday, so that it occupies 5 days instead of 4.25 days approximately.

hope i m making it clear for you.

awaiting a response

eg.jpg

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Gantt Chart Activity

A
Ammar Abbas 👤 Member for 15 years 4 months

I am a beginner at primavera, i need to know how one can change gantt chart to show one day activity occupying the whole duration, like in this example activity starts somewhere mind sunday and ends in mid Thursday, where as I want it to start from the end of Saturday (start of Sunday) and continue till the end of Thursday, so that it occupies 5 days instead of 4.25 days approximately.

hope i m making it clear for you.

awaiting a response

eg.jpg

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts