Urgent help pls regarding re-scheduling (F9)

G
G T 👤 Member for 15 years 5 months

Dear Forum could u pls help me ... its very utgent...

 

I was given some schedule prepared in P3 so when I reschedule it to some other dates (F9) early activities dont move they are frozen. Data date line keeps moving  but activities not... I even inserted some dummy activities linked to nothing but they stuck at start date and dont move....

 

 

Thanks very much

G

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

The Exact Definition of Open End Activity

M
Mai Tawfeq 👤 Member for 16 years 3 months

Dears:

 

A discussing was going on in regard of exact definition of open end activity.

Some said that open end activity, the activity without successor and others said that open end activity which is belong and come under open end track or path even the activity has predecessors or successor but the end of track where it belongs is opened with no links to project completion date.

 

So now my dear I need some expertise opinions.

 

Thanks. 

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Updating Physical % Complete with MS Excel & P6

Hello, 

Summary: I am updating numerous traits of selected activities ( including physical % complete) for a project by exporting from P6 to Excel 2007 on Windows XP, updating the traits (including physical % complete), and then importing back into P6.

 

Problem: All the traits are changing almost perfectly except for Physical % complete, which doesn't seem to update at all.

 

Full Description:

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

example of Full Design and build construction project WBS

L
lolo choise 👤 Member for 15 years 3 months

Hello,

i am new on this forum

i have to build a WBS for a construction project including design and procurement

i don't know exactly where to insert the shop drawing in my WBS, and how to develop the constrcution phase,

here is my proposition, if somebody can give me advice....   it will be great

regards

lolo

 

Generalities

                Key Construction milestones

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

What is online scheduling?

Online scheduling is the usage of competitive analysis (or online algorithms) on scheduling problems. Online algorithms is characterized by making decision "online", which means a point in the time axe. In this point of time, we can not see the future jobs or tasks, whereas we only know the jobs or tasks before or at this point of time.

------------------------------------------------------------------------------------------------------------------------------------------------------------------

 

[advert link removed by Gary Whitehead]

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

NEC Contract I need Urgent Answer Please Reply

J
John Peter 👤 Member for 15 years 3 months

Oh Hi 

I want to know my NEC contract and from some discussion on this forum  i understand 

1) This is New Engineering contract and created to resolved disputes when things goes wrong mainly in construction contract.

2) It clearly define the responsibilities of sponsor and contractor

3) Reporting time is same as normal construction contract in which contractor produce reports for client in monthly

4) And I assume that the change in contract can be done by a clause define in the contract how to accept changes.

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts

Forum Sponsor

Top Posters

Neil Atkinson
5 posts
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts