We are on a mission to discover the origins of Rolling Wave planning – where did the idea come from? Who used it first?? Is it an EV concept borrowed by schedulers or the other way round??? Any ideas or authenticated sources would be appreciated.
Rolling Wave Planning
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi
I came across the following links, check out
http://www.projectsmart.co.uk/pdf/rolling-wave-planning.pdf
http://www.catalystpm.com/NP02.pdf
Regards
Shahul
M. KHAN,
Thanks for the explanation - "WBS being vertical and Schedule as horizontal"; and Rolling Wave is horizontal;
But isn't it that a rolling wave goes up and down? What if a Rolling Wave goes up (higher than normal), can we call it a Schedule Tsunami?
cheers
Patrick Weaver
Rolling wave planning and Progressive elaboration are both the charaterstices of project.They are two very important concept to understand by every Project Manager and Project Planner.Sometimes called as a PMISM for Project Management Institute PMI.
I am talking her big construction projects and when they starts most of the items defines in broad terms . when we starting developing those projects we get more refine information and more definate terms.
Like first high level project statment and than into detail project statment in terms of detail WBS.
AS you know WBS structure as being vertical and the schedule as being horizontal, then progressive elaboration would be a vertical process, while rolling wave would be horizontal process..
In nutshell Progressive Elaboration suggests "gradual" refinement of SCOPE. Rolling Wave Planning suggests "gradual" refinement of SCHEDULE.
I hope this wil answere the question.I will suggest if you want to know more try PMBOK 4th Edition of PMI or Rita PMP.Both are the best books on Project Management with tons of best practices.
M Khan PMP 07917827290
Patrick Weaver
Rolling wave planning and Progressive elaboration are both the charaterstices of project.They are two very important concept to understand by every Project Manager and Project Planner.Sometimes called as a PMISM for Project Management Institute PMI.
I am talking her big construction projects and when they starts most of the items defines in broad terms . when we starting developing those projects we get more refine information and more definate terms.
Like first high level project statment and than into detail project statment in terms of detail WBS.
AS you know WBS structure as being vertical and the schedule as being horizontal, then progressive elaboration would be a vertical process, while rolling wave would be horizontal process..
In nutshell Progressive Elaboration suggests "gradual" refinement of SCOPE. Rolling Wave Planning suggests "gradual" refinement of SCHEDULE.
I hope this wil answere the question.I will suggest if you want to know more try PMBOK 4th Edition of PMI or Rita PMP.Both are the best books on Project Management with tons of best practices.
M Khan PMP 07917827290