NEC - EoT Entitlement
Am I right in my thinking with the following.....
I have assessed a PMI and impacted the last Accpeted programme, as a result there is a 2 day impact to Planned Completion.
However when I then put these works in the current Draft Programme (with submission imminent), the is no delay impact as there is 2 days float and therefore the works slot in and and become Critical.
My view is that we are still entitled to the 2 day delay costs and therefore the Contract Completion should move out to accommodate the 2 days (albeit with