Need help in preparing a schedule for a project plagued with problems

Hello Every one,

 

I am a planning engineer for 15.6 KM Road project which consists of 4 Tunnels and 3 Bridges. This project is being executed in a hilly terrain. This project started way back in 2006. This project is being plagued with problems. Around 2km of road is in land acquisition problems. Rest of the portion is completed. Recently one of the tunnel front portal collapsed since it's residing on man made debris. So we are waiting for an alternative design. I am actually trying to prepare a work program for this project.

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Benifit Plan Utilization in Primavera P6

S
SM PUM 👤 Member for 14 years 7 months

Hi All,

I was established Spending plan for a project in Primavera P6 ,and while doing so I have come across the "Benifit Plan"  column in "Spending Plan" tab.I have tried to seach about this but have not yet cleard my concept.can anyone please tell me that what is the purpose of "Benifit Plan" column?

Regards.

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Benchmarking Programme Requirements - ITT

Hi all,

I am looking to benchmark standard programme requirements in an Invitation To Tender. There will always be a certain level of project specific requirements, however does anyone know of an industry standard?

I would typically expect a document to reference (but not limited to) DCMA 14 Point Assessment Integrity Check, APM Guidlines etc.

I would welcome you comments.

 

Karlos

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

How to filter out the activities having overallocation

S
SM PUM 👤 Member for 14 years 7 months

Hi All,

In my schedule there are some resources showing over-Allocation.I want to perform resource levelling.The issue is that i am not able to sort out a method to separate the activities that have resources over allocated.For example,mason is Overallocated and is shown in Red in "Resource usage progile" for the month of december.Now i know that in December my Resource is overallocated.but how to filter out the relevent activities because i shall need total float values for resource levelling.

 

Regards,

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts

P6 Plan Help

R
Rhys Parry 👤 Member for 14 years 9 months

I am using Primavera P6 and I have a plan in which I have split down to Daily, Weekly, Monthly, Quarterly, Six Monthly and Annually activities.

I have the planned duration for each and I was wondering is there any need in putting a duration in if I have activities split into different sub headings.

Is it possible to put a constraint on each activity within each sub heading for daily, weekly, monthly.....

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts