No

Planned Dates, Duration & Scheduling in P6

I seek help from the forum members on the following:

 

When I schedule P6, the non progressed activities acquire the data date as their Planned Start Date and the Original Duration also changes. I guess some setting may be wrtong, but I couldn't locate the wrong setting. Can someone please guide me?

 

Thanks in advance.

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

External Relationships in P6v8

Attention fellow Planners, I need help to fix our level 3 construction schedule development in P6. The situation is described below:

1) There is 3 project files involved as follows:

File 1: Current EP Schedule @ Production Node

File 2: Update/Back-up EP Schedule for Month April @ Update Node

File 3: Level 3 Const Dev't Schedule @ Development Node

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

PLEASE CLARIFY THE BELOW DOUBTS.!!!

Hello sir,

I have big doubts in primavera P6

1) While loading the resourcesThe avaliability of resources where we have to give?

2)In resource coloumn What is ment by MAXUnits/TIME

3)While loading the resources for 1 activity we need 5 helpers in that case we have to create 5 different resources or only we can create helpers and quantity how please explain?

4)What is meant by level of programme

5)How To calculate the total flote and critical path and Earned value analysis?

6)Please help me with some electrical and instrument activities

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

Splitting activities in P6

Hi

The normal form of splitting activities is to use the 'Suspend' and 'Resume' functions in P6. However I find that this does not work in my P6 system.

The activity does not indicate a stop and restart date in my Gantt chart.

Is there something I am doing wrong.

Any help will be greatly appreciated

Thanks

 

Uduma

 

 

 

 

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

Planning guide for re-measured contract

Hi Friends,

Baseline Approved base on the Contract BOQ. Since its a re measured contract, monthly my quantities vary.

Please suggest me a proper way to monitor the progress, provide Plan % progress (Is it base on the Contract BOQ) then how about for the actual % progress? theres a new and deleted activities as well. I prepare the remaining quantities base on the contract BOQ however, still not accurate because of the changing quantity.

 

Hoping for response.

 

Thanking you,

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

how to control a design phase in a EPC project?

J
Jian Liu 👤 Member for 15 years 3 months

HI!

I want to get some advice for schedule and track design phase in a EPC project.

I cannt give you more detail about our company's process. it's too bad to monitor a design schedule well.

I just want know how about yours.

some roles in the design phase PM PE PC LE  E .

many thanks!

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

Civil Infrastructure project help

I
imran khan 👤 Member for 14 years 6 months

Hi Everybody!!!!!

 

  I have been given a project of already built 30 villas and the project is planning of road, water supply, and electricity supply to those villas. I dont have any idea since previously i was involved with MEP building planning.....so could anybody out there will help me out with their valuable suggestions!!!!!

 

Regards,

Imran

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

Daily Qtys - P6

L
Luke Charet 👤 Member for 16 years 10 months

Morning All,

Is it possible to add daily qtys into P6. Our engineers enter daily qtys into a spreadsheet and I would like to track it in P6. I am currently focused on tracking of crushing - I update the programme weekly and P6 spreads my qty evenly as an actual however I would like to add my daily qtys manually. Not sure if you can do it and some will argue is it worth it. However it sits on the critical path and I would like to manage it more closely.

Thanks

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

Baseline Comments Received

Baseline Comments.

Some of the comments for a baseline are listed below. Appreciate your comments.

1. Project Milestones. Is it compulsory to have successors to milestones.
2. Restriction of maximum duration for activities to 20 days. Some long lead items are 50 days or more. How to cut short. Any hard and fast rules.
3. Key Milestone Should have zero float.
4. Restriction / limit of total number of critical activities.

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts

Hi, everyone. What duration type you will choose? then what percentage type you will use to engage your duration type. Or it is

L
louis hung 👤 Member for 18 years 2 months

 

Regarding you had completed resource loading and been authorized of your baseline.1.Fix Duration &Units2.Fix Duration &Units/time3.Fix units4.Fix Units/timeThen what percentage type you usually adopt.1.Duration2.Physical 3.Unit.Actually, I am not very sure how it engage this two elements to make it work well.Maybe you guy can provide your well experience here.Thanks!

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts